Time extensions in construction contracts
Construction contracts generally allow the construction period to be extended where there is a delay that is not the contractor's fault. In the United States, this is described as a time extension. The UK equivalent is an extension of time (EOT).
When it becomes reasonably apparent that there is, or that there is likely to be, a delay that could merit a time extension, the contractor gives written notice to the contract administrator identifying the relevant event that has caused the delay. Time extensions are granted based on the contractor being able to demonstrate that the delay was caused by events beyond their control. The contract guidelines typically specify the provision of time extension requests.
There are various circumstances in which time extension requests will be valid, including:
- Delays are caused by the owner changing the design.
- A delayed start to the works by request of the owner.
- Site conditions (e.g. sub-surface conditions) that differ from the project plans.
- Exceptionally adverse weather.
- Variations to the original scope or contract required by the owner.
- Force majeure.
- Legal issues that affect project completion or the contractor’s performance.
- The supply of materials and goods by the owner.
There are various circumstances in which time extension requests will be deemed invalid, including:
- Delays are caused by subcontractors.
- When the workforce is insufficient.
- The contractor underperforms, i.e. by procuring long-lead items.
- Delays caused by normal adverse weather conditions.
- Where there is inadequate evidence that irrecoverable delays have not been caused by the contractor.
In order for a time extension to be granted it is important that the contractor is transparent and communicative in their dealings with the owner and the project team. The project manager must be informed at the earliest opportunity and, if they deem it valid, they will submit a formal time extension request. For further information, see What should be included in a time extension request?
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Art of Building CIOB photographic competition public vote
The last week to vote for a winner until 10 January 2025.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.
20 years of the Chartered Environmentalist
If not now, when?
Journeys in Industrious England
Thomas Baskerville’s expeditions in the 1600s.
Top 25 Building Safety Wiki articles of 2024
Take a look what most people have been reading about.
Life and death at Highgate Cemetery
Balancing burials and tourism.
The 25 most read articles on DB for 2024
Design portion to procurement route and all between.
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.